project

South Jordan, Utah

This industrial warehouse building in the Daybreak Commerce District in South Jordan, Utah, is an excellent example of tilt-up construction that exceeded owner expectations. The project can serve as a light industrial facility, warehouse, storage, and distribution center. The project uses 50 concrete tilt-up panels.

Despite being constructed during the initial stages of the pandemic and shutdowns, Daybreak Commerce finished on time in eight months. Sean Campbell Construction effectively kept the workforce safe from exposure and completed the project on schedule.
Relevance
  • Concrete tilt-up construction
  • Rapid schedule

The Project Stats

$14.4 M
Contract Value
10
Month Construction Schedule
110,022
Square Feet Of Construction

Special Features

Building 1
  • 50 panels
  • On-time schedule, with significant supply chain and workforce challenges
footercontactimage
homemapicon385 West 2880 South
South Salt Lake, UT 84115
homephoneicon+1 (385) 528-3601
homemailiconestimating@campbell-co.com

Request a Bid or Contact Us


© 2024 All Rights Reserved