project

Lehi, Utah

The Holbrook Industrial warehouse and distribution center in Lehi was built with tilt-up construction. The modern black-and-white aesthetic was chosen to appeal to tenants looking for a modern space to house their day-to-day operations but can also serve as an industrial warehouse and distribution center.
Relevance
  • Concrete tilt-up construction
  • Multiple sequenced buildings
  • Rapid schedule
  • 500,000 cubic yards of dirt moved

The Project Stats

$44.5 M
Contract Value
29
Month Construction Schedule
909,000
Square Feet Of Construction

Special Features

Building 1
  • 55 panels
  • 9 month schedule, completed in 8.25 months
Building 2
  • 73 panels
  • 9 month schedule, completed in 8.25 months
Building 3
  • 84 panels
  • 9 month schedule
Building 4
  • 104 panels
  • 11 month schedule, completed in 10 months
“I have really enjoyed working with Campbell Construction these past few years. The thing I appreciate most is their responsiveness. When things don’t go as planned, they are quick to respond and find a solution. I am sure we will continue to work together on future projects.”
footercontactimage
homemapicon385 West 2880 South
South Salt Lake, UT 84115
homephoneicon+1 (385) 528-3601
homemailiconestimating@campbell-co.com

Request a Bid or Contact Us


© 2024 All Rights Reserved